Tag: KPTC

  • Cable stringing deadline unrealistic: Karnataka MSOs

    Cable stringing deadline unrealistic: Karnataka MSOs

    BANGALORE: With the one-month time given to MSOs to implement design guidelines issued by the Karnataka Power Transmission Corporation (KPTC) about to expire, the Multi System Operators (MSO) argue that it would be impossible to adhere to the guidelines in the given timeframe and against the present set up.

    “The KTPC’s design for stringing up of cables cannot be implemented at such a short notice. It’s too fancy and such standards should have been laid down at the initial stage itself,” opined an MSO.

    “In many cases their low tension (LT) lines are too low, maintaining the clearances between the power lines and the cable wires and the cable wires and the ground would be impossible. The guidelines indicate that the cable wire must be at least 10 feet (3.05 meters) from the ground and at least 4 feet (1.2 meters) below LT wires; many of their LT wires are at only 10 feet from the ground. Also in many case, there is no room between the LT wires and the walls or other abutments to string the cables almost 7 feet (2 meters) from the pole,” the MSO added.

    KTPC general manager (Technical) vide his circular dated 21 July has laid down guidelines for laying of OFC/co-axial cables on distribution network after the sad incident which claimed seven-year-old Anish’s life on 12 July when he came in contact with a loosely hanging ‘live’ cable wire.

    Copies of the circular with guidelines with drawing and a checklist have reportedly been sent to a number of persons at all ESCOMs. The action taken for implementation of the circular guidelines and its execution will have to be furnished to the GM (Technical), KPTCL within 30 days of the issue of the circular.

    Some of the guidelines in the circular specify the size of the messenger wire as 3.15 mm, 45 kg/sq. mm class GI wire, stating that cable tapping should not be done at the poles, but at-least 2 meters away from the poles. The minimum ground clearances have been specified as 5.8 metres across road and 3.05 metres along road. The communication/ TV cable wires should not run above power lines, they must always be below power lines. The clearance between the power line and messenger/cable wire has been specified as 1.8 metres when run under an 11KV line and 1.2 metres when run under a LT line.

    In a separate development, Bangalore Electric Supply Company (Bescom) has re-iterated it’s threat to cut illegal cable wires from 19 August onwards. MSOs such as ICE1 and ICE2, among others, would be effected the most as per industry sources.

    The Bescom had given cable operators time till 16 August to come up with proposals to help streamline the drawing of cables in the city. If the cable operators did not contact Bescom by 16 August Bescom would be forced to remove all illegally drawn cables and would not be responsible for any inconvenience caused to the public or to the illegal cable operators.

  • Bangalore cable tragedy: Officials unclear about third probe

    Bangalore cable tragedy: Officials unclear about third probe

    BANGALORE: Karnataka government officials are of the opinion that another inquiry report to probe the circumstances that led to a seven-year old boy’s death is not required, as per media reports.Earlier, Bangalore Electric Supply Company (Bescom) and the chief electrical inspector to the government (CEIG) had submitted their inquiry reports.

    On 15 July, Karnataka chief minister Dharam Singh is purported to have ordered a third probe when he visited the boy’s house. According to authorities, it is unclear whether or not he meant another inquiry by principal secretary Ranganath.

    As reported earlier, Bescom had initiated a cable cutting frenzy holding a wrongly strung cable TV wire responsible for the tragic event. A compete blackout of TV by the cable operators was averted with CM’s intervention. 

    A preliminary inquiry initiated by Bescom’s chief engineer (CE) had found BCC responsible for the tragedy, along with the concerned Bescom staff.

    Ranganath had obtained the details of the two investigations and a report from the Karnataka Power Transmission Corporation (KPTC). Action has been initiated against the four Bescom persons named – an assistant executive engineer, engineer, a junior engineer and a linesman, all of whom have been suspended and are facing an inquiry.

    According to reports, 20 August has been fixed as the deadline to complete the comprehensive review of all hazardous cables. Ranganath is to hand over the KPTC’s report to the CM early next week, based on which the CM is expected to pass orders.